|

CONSTRUCTION
PROGRESS SCHEDULE
Before
a professional progress manager will begin a major
construction project, one of the first steps to be
undertaken is the creation of a Construction Progress
Schedule. The importance of establishing a progress
schedule can be seen in the saved hours of labor,
reduction of construction conflicts by overlapping
trades and avoidance of delays in the delivery of
long lead items.
How
does one establish a progress schedule? The first
step is to make a list of every trade (sub-contractor
and vendor) and when they are scheduled to begin their
work. Next, record the scope of work to be completed,
as well as the number of days the work will take to
be completed. It is important to note two points.
First,
if one sub-contractor must complete a specific task
or line item before another trade can begin their
work, the first contractor must be scheduled with
ample time to complete their task.
Secondly,
if an item such as specialty windows, pews or custom
seating, custom dyed carpeting, artwork or other items
scheduled to take many weeks or months for fabrication
and delivery, these items should be ordered in advance.
Before signing a contract with vendors of stained
glass, pulpit or bimah furnishings, custom seating
or pews,
it
is very important to discuss delivery dates from the
date of a signed contract. Many pew companies may
require 9-12 weeks for delivery from the date of a
signed contract and approval of finishes and fabric
samples. It is also not uncommon to wait six months
or longer for custom-made art or stained glass windows.When
creating a progress schedule, allow ample time to
complete the assigned tasks.
Trades
that work outdoors, may require longer time due to
weather conditions, especially during the autumn and
winter months. When scheduling a multi-month project,
it is wise to allow a few floating days to allow for
non-productive periods due to weather, delays in receipt
of materials, illness, inspection delays, etc.
The
purpose of a construction schedule is to see on paper
if all of the trades have ample time to complete their
sub-contracts with a minimum of conflict. If a construction
progress schedule is completed properly, one should
be able to see how long it will take to complete the
entire project.
A
progress schedule allows you to tell instantly if
a PraiseBuilding project is on schedule. This progress
schedule can become an important part of the check
and balance system of managing the project.
By
Stephen Ferrandi, Director, KLNB Religious Properties
Stephen
Ferrandi is the Director of KLNB Religious Properties,
a real estate firm serving religioius clients in Maryland,
D.C., Pennsylvania, and Virginia. He is one of the
top experts in land development in the region. Mr.
Ferrandi frequently contributes real estate related
articles to both print and online publications.
|